Saturday, December 27, 2025

23-28 December 2025 Christmas in the Woodlands.

 After stopping at the house to check on the septic tank, we drove down to the Woodlands for Christmas with Cynthia and Felix. We spent Christmas Eve at Laurens house and got to see the grand nieces, meet Laurens new boyfriend and his kids. Our other two neices, Sydney and Emilly, were there as well. We had not seen them in several years and it was great to catch up with them. As usual, the the gift exchange was crazy fun chaos! The little girls each got a karaoke box from Cynthia with sound effects. The noise from those was enough to drive everyone home! Christmas morning we went back to Laurens for breakfast and to see what the grandnieces had gotten from Santa Claus. They both received a huge Barby Doll House that included a pool, elevator, bathroom (with sound effects) and a kitchen! Even the teenage girls were having fun playing with them! Later that day we had wonderful Christmas Dinner back at Cynthia’s and Felix’s. 


Cynthia with Lauren, Emilly and Sydney


Chaos of gift opening.


15-23 December 2025 Trim Carpenters Start

 The tile and floor contractor continued to work on their installation. They completed the EVP install and tile floor install except for the grouting. The trim carpenters started their work. On Davids Suggestion, we met at the house with the trim carpenters and walked through how we wanted the closets and pantry configured. If we had not suggested it, who knows what we would have gotten installed. They are also installing the doors and attic access stairs. We also provided they pictures of how we wanted the trim around the front and back doors. We picked up a couple of night stands from an online seller. They needed some work. On Wednesday, Leslie sanded the tops down and stained them while David repaired the ethernet cables, finished installing the conduit and filled in the trench. The Trim carpenters are making quick work of trimming out the house and appear to be doing an excellent job at it. They showed up Monday (22 Dec) to install the septic system. David met with Kelby and the Septic contractor to work out where he wanted the sprinklers installed and to check they knew where the wire conduits were so they did not cut them. As he pulled up, he could hear they were jack hammering rock. Sure enough, they only dug down a couple of feet before hitting solid rock. They had to jack hammer through 10 feet of limestone to dig a hole deep enough to put the tank. David had expected some rock layers, but not ten feet of solid limestone. We went out on Tuesday as we were leaving town to see how they had done and the tank was installed (although they still had some connections to complete). We haven’t heard how much extra it is going to cost for the effort to cut through the rock yet. There is a “rock clause” in the contract to give them relief. There is a large pile of rock that will have to be disposed of as well. David asked if they could put it in the low corner in the southwest corner of the lot rather than pay to haul it away, but has not heard back yet. We are going to have to do something different with the propane tank rather than have to dig another whole in the rock. The good news is that house sits on top of this rock shelf, so the foundation is pretty solid. 



Our septic tank

Chipping away at the rock




Tank in the ground


Big pile of rock!



Monday, December 15, 2025

7-14 December We Have Floors (mostly)!

 This week, David was in Albuquerque for work most of the week. While he was gone, they finished the tile work in the guest bath but apparently ran out of material to finish the master bath and powder room. They laid the Engineered Vinyl Plank (EVP)down in most of the house but ran out of planks and underlayment before they finished and stopped work. But they did finally cut those two bolts sticking out of the concrete off before they laid the EVP over them! Leslie met our realtor, Laurie, at the house and they went over all the paint colors that have to be selected. For all the cabinets, walls, trim, doors, etc. On Friday, David went out to the house and met the installer for the mantle. We selected a 135 year old hand hewn barn beam from a local barn with some hand cut mortises. The beam is white oak and extremely dry and hard. They sent one small guy, Evan, to do the install. There was no way he was going to lift that beam by himself. So, David spent 6 hours helping Evan cut, fit and mount the mantle in place. The wood was extremely hard and the cuts had to be done with multiple shallow passes or the saw would bog down and stop. Evan spent quite a bit of time trimming the side pieces so they would fit very tightly. Imagine taking a hard old bent and twisted beam and try to mount it square and level with an unlevel stone ledge and unsquared walls. But Evan is a pro. It turned out beautiful! On Saturday, we picked up some electrical conduit and ran the data cable from the house to the shop through them. Unfortunately, David realized the last straight pipe was too long to make the corner after he had already glued it in place. He tried to cut it with the circular saw while holding the wires out of the way. But caught three of the four cables with the saw and cut them. Now he will need to spend a few hours splicing tiny Ethernet cables together before we can finish the job and fill in the trench. We were sooo close to finishing! 

Cutting the mantle on the back patio

Finished Mantle. You can also see the EVP

Hand cut mortice

Tight corner joints



Sunday, December 7, 2025

1-7 December Burrr

 Monday night was our first below freezing night since last winter. In preparation, we turned on the propane heaters to check they were working. Normally, when the thermostat turns on one of the two heaters, there is a click followed by the exhaust blower turning on. We noticed that the upstairs heater did not start the exhaust fan when the thermostat clicked on. The downstairs furnace clicked on and ran fine. David checked the fuse for the upstairs furnace and it was blown. He put in a new one. Same response. David checked the new fuse and it too was blown. We got through the night with the one heater and the electric fireplace heater. The next day, David disassembled the upstairs furnace and found this huge mud-dauber wasp nest was jamming the exhaust fan! He cleaned it out, got it all back together (with no spare parts!), put in a new fuse and all works now. We won’t need it for a couple of weeks, but knowing it is fixed and ready to go for the next freeze is a comfort. On Wednesday we headed over to Burleson to view the cleaned up version of our future mantle and to check its color against the stone it will be above and the wood floor planking. It’s going to be awesome. We then headed down to Midlothian to pick up a kitchen table Leslie had discovered on Facebook Marketplace. Carrying the 5 foot in diameter glass top and getting it back to Cresson was a challenge but we were successful without hurting ourselves or breaking anything. They continued working on the tile and flooring in the house. It’s going slower than they said it would, but it's looking great. We went up to Fort Worth to pick out the counter tops. We picked one slab of granite with a leathered finish that we had to have for the island. We then picked out quartz counter tops for the rest of the kitchen, bathrooms, utility room, coffee nook and pantry. They are putting portable heaters in the house to keep it from freezing during the cold nights. Everything is waiting for them to finish the tile and flooring. On Saturday, we dropped some stuff off at the shop and went inside the house to check on progress. Most of the tile work is completed and they are laying the underlayment for the flooring. David saw they had run the underlayment into the guest bedroom so he went to check on the two bolts sticking out of the foundation from their mistake back in August. David has been on them to cut those bolts off since August because they were a safety hazard. They kept telling him they would be taken care of, then that the flooring guys would take care of them. We have reminded each new build supervisor about them and even the flooring guys before they started. But sure enough, there they were sticking up through holes in the underlayment! On Saturday they also dug a trench from the house to the shop and ran a 2 inch pipe to carry the power line from the house to the shop. But they put it right next to the wire routing pipe that David has been trying to get them to fix since they bricked the house. Now it is going to be even harder for them to fix it since there is less room. Sigh. 

Mud-dauber Nest pulled from the furnace

Bolts sticking out of the foundation

Master Bath Tile

Floor of the utility room

Guest Bath

Wire Routing Pipe back in the corner embedded in the wall.